施工步骤:
1.地基表面必须洁净、永久性、干燥、强度大于C20,没有结构上的缺陷。
2.采用AB多功能界面剂(约2~6小时后)开始自流平施工。
3.将水6.5kg左右倒入,边搅拌边倒入至均匀,无团资料。将混合料倒出所施工区域,均匀铺开,用专用齿口刮板控制厚度。刚施工好的区域避免阳光直射和强风。
4.在自流平初凝前用消泡滚筒扎地面以排除混合时带来的空气。
Construction
Steps:
1.The
ground should be clean, durable and dry with hardness higherthan C20, without
any crack.
2.Start
self leveling procedure after use the AB Multifunctional Interfacial Agent
(about 2 to 6 hours)
3.Pour
about 6.5kg water to a vessel, and a pack of AB Self Leveling Concrete as stir
to make them mix evenly. Pour the mixture to the con-struction parts needed
evenly and control the thickness by sawtooth blade. Prevent the ground laid
from direct sunshine or strong wind.
4.Press
on the surface by bulb removing roller before stable condensation to remove
thered-undant air.